Project experience Hydrotherapy pools
Sector experience Healthcare
Services Planning advice
Design
Construction
Year completed 2013
Client Chelsea & Westminster Hospital
Contractor London Swimming Pool Company
 
 

Chelsea & Westminster Hospital’s hydrotherapy pool underwent complete renovation. The pool is used for rehabilitation of post-operative and injured people and the less able-bodied, enabling them to benefit from the therapeutic benefits of water.

The renovation project involved replacing the old interior liner with a custom-made high quality lining. The engineers had to drill through 16 inches of concrete to accommodate all the new return and suction lines necessary for the level of circulation required for a top quality, modern hydrotherapy pool.

The plumbing had to run through the ceiling of the hospital records storage room, a space measuring 18 inches high and overcome the difficulty of bending pipes around existing ceiling supports.

The old plant was replaced with highly efficient filters and pumps to obtain the proper turnover rate. Glass beads filtration media was used instead of sand as they provide superior filtration and lasts longer.

The rejuvenated facility was re-opened in May 2013.

Partners: Management Contractor: Bisley Contracting


Chelsea & Westminster Hospital’s hydrotherapy pool underwent complete renovation. The pool is used for rehabilitation of post-operative and injured people and the less able-bodied, enabling them to benefit from the therapeutic benefits of water.

The renovation project involved replacing the old interior liner with a custom-made high quality lining. The engineers had to drill through 16 inches of concrete to accommodate all the new return and suction lines necessary for the level of circulation required for a top quality, modern hydrotherapy pool.

The plumbing had to run through the ceiling of the hospital records storage room, a space measuring 18 inches high and overcome the difficulty of bending pipes around existing ceiling supports.

The old plant was replaced with highly efficient filters and pumps to obtain the proper turnover rate. Glass beads filtration media was used instead of sand as they provide superior filtration and lasts longer.

The rejuvenated facility was re-opened in May 2013.

Partners: Management Contractor: Bisley Contracting


Interested in this project?
Call 020 8605 1255
OR
 
 
 
Downloads
  • London Swimming Pool Company brochure
    London Swimming Pool Company brochure
    20pp 2.31MB
    Download
  • London Swimming Pool Company brochure
    London Swimming Pool Company brochure
    20pp 2.31MB
    Download
 
 
 
Enquire
 


Also by London Swimming Pool Company

London Swimming Pool Company address and contact details

London Swimming Pool Company Ltd
Unit 1
Shannon Commercial Centre
Beverley Way
New Malden
KT3 4PT
Tel: 020 8605 1255
View on map
 
Follow London Swimming Pool Company
 
Not found what you're looking for? View other options

Ask London Swimming Pool Company about

Chelsea & Westminster Hospital hydrotherapy pool